Construction Updates

Live view

You can view a recent photo of the jobsite by clicking the button here. 

July 2024

The following work took place:

  • Transformer was installed and switchgear was energized.

  • Storm detention system was installed.

  • Exterior sliding panels have begun being installed.

  • Painting and ceiling systems are being installed.

June 2024

The following work took place:

  • The majority of the exterior windows were installed.
  • Air vapor barrier around the perimeter of the building was completed.
  • Decorative parapet was framed.
  • Taping is ongoing at the interior walls.
  • Electrical in-wall rough-in was completed.