Southington public library

Construction Updates

Live view

You can view a recent photo of the jobsite by clicking the button here or watch a timelapse video. 

October 2024

  • Light fixtures are all installed, and lighting controls are underway.
  • AV and fire alarm devices have been installed and tested.
  • Mechanical start up and testing is underway.
  • Bathroom accessories have been installed.
  • Interior and exterior signs have been hung.
  • Fence for the children’s reading plaza has been installed, along with the exterior sliding door.
  • The south parking lot has been paved and line striped.
  • Privacy fencing has been installed.
  • Landscaping and hardscapes are nearing completion.
  • Cleaning is ongoing.
  • Shelving is being assembled.
  • Elevator commissioning is completed.
  • Project has achieved temporary certificate of occupancy.
  • Furniture is being installed.

The following work is upcoming:

  • The interior children’s sliding door to be installed.
  • Program room’s operable partition to be installed.
  • Moving process to begin.

September 2024

The following work took place:

  • Ceiling tiles are being placed.
  • Floor preparation and carpet tiles are being installed.
  • Sandstone exterior stone paneling is being mounted.
  • Bathroom tile is being grouted.
  • Reference desk is being assembled on the second floor.

AUgust 2024

The following work took place:

  • Main entry doors were installed.
  • Main entry exterior ADA ramp had concrete poured.
  • Site curbs and exterior lighting bases have started.
  • Floor tile in bathrooms is underway.
  • Light fixtures started being installed.

Topping out ceremony

What is a topping out ceremony and why do we do it in the construction industry?

Floor plans