Southington public library
Construction Updates
September 2024
The following work took place:
- Ceiling tiles are being placed.
- Floor preparation and carpet tiles are being installed.
- Sandstone exterior stone paneling is being mounted.
- Bathroom tile is being grouted.
- Reference desk is being assembled on the second floor.
AUgust 2024
The following work took place:
- Main entry doors were installed.
- Main entry exterior ADA ramp had concrete poured.
- Site curbs and exterior lighting bases have started.
- Floor tile in bathrooms is underway.
- Light fixtures started being installed.
July 2024
The following work took place:
- Transformer was installed and switchgear was energized.
- Storm detention system was installed.
- Exterior sliding panels have begun being installed.
- Painting and ceiling systems are being installed.
June 2024
The following work took place:
- The majority of the exterior windows were installed.
- Air vapor barrier around the perimeter of the building was completed.
- Decorative parapet was framed.
- Taping is ongoing at the interior walls.
- Electrical in-wall rough-in was completed.