Southington public library

Construction Updates

Live view

You can view a recent photo of the jobsite by clicking the button here. 

September 2024

The following work took place:

  • Ceiling tiles are being placed.
  • Floor preparation and carpet tiles are being installed.
  • Sandstone exterior stone paneling is being mounted.
  • Bathroom tile is being grouted.
  • Reference desk is being assembled on the second floor.

AUgust 2024

The following work took place:

  • Main entry doors were installed.
  • Main entry exterior ADA ramp had concrete poured.
  • Site curbs and exterior lighting bases have started.
  • Floor tile in bathrooms is underway.
  • Light fixtures started being installed.

July 2024

The following work took place:

  • Transformer was installed and switchgear was energized.
  • Storm detention system was installed.
  • Exterior sliding panels have begun being installed.
  • Painting and ceiling systems are being installed.

June 2024

The following work took place:

  • The majority of the exterior windows were installed.
  • Air vapor barrier around the perimeter of the building was completed.
  • Decorative parapet was framed.
  • Taping is ongoing at the interior walls.
  • Electrical in-wall rough-in was completed.

Topping out ceremony

What is a topping out ceremony and why do we do it in the construction industry?

Floor plans